Organization HVAC contractor; Solids Handling Upgrade 14 mentions · 2026-01-22 to 2026-04-02
Solids Handling Upgrade Cranberry Township Board of Supervisors Northfield Road Storm Sewer Upgrades McCurley Houston Electric Inc Community Park North Improvements Fryer Excavating Shipley Plumbing LLC Kukurin Contracting Inc Community Park Glen Eden Development Company Thomas Construction Inc Michael Malak Karen Newpol Bruce Mazzoni John Skorupan
Article Board of Supervisors 2026-04-02
20. Contract Order #2025-180 - Partial Payment – Community Park North Improvements – 133/2026 General Contractor Motion to approve a partial payment for general construction for Community Park North Improvements to…
Article Board of Supervisors 2026-04-02
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $31,441.77. Attachments Name Download Ext. Filesize Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - H…
Article Board of Supervisors 2026-04-02
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $31,441.77. Votes: Yes 5 , No 0 , Abstain 0 Connect With Us © PROVOX Systems, Inc. --- Menu Welcome Municipality Committe…
Article Board of Supervisors 2026-03-26
At the April 2, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $72…
Article Board of Supervisors 2026-03-26
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $31,441.77. Attachments Name Download Ext. Filesize Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - H…
Article Board of Supervisors 2026-03-26
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $31,441.77. Votes: Yes 5 , No 0 , Abstain 0 Connect With Us © PROVOX Systems, Inc. --- Menu Welcome Municipality Committe…
Article Board of Supervisors 2026-02-05
27. Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - HVAC Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $55,100.88. VOTING Mo…
Article Board of Supervisors 2026-02-05
25. Contract Order #2025-178 - Change Order - Northfield Road Storm Sewer Upgrades 14/2026 Motion to approve a change order for Northfield Road Storm Sewer Upgrades to Fryer Excavating in the amount of $19,284.58. …
Article Board of Supervisors 2026-02-05
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $55,100.88. Attachments Name Download Ext. Filesize Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - H…
Article Board of Supervisors 2026-02-05
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $55,100.88. Votes: Yes 4 , No 0 , Abstain 0 Connect With Us © PROVOX Systems, Inc. --- Menu Welcome Municipality Committe…
Article Board of Supervisors 2026-01-22
26. Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - HVAC At the February 5, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handling Upgrade for HVAC wo…
Article Board of Supervisors 2026-01-22
At the February 5, 2026 Regular meeting, the Board will be asked to consider approval of a change order for the Clubhouse roof replacement to Grahamboys, LLC. for a deduction in the amount of $2,188.00. 24. …
Article Board of Supervisors 2026-01-22
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $55,100.88. Attachments Name Download Ext. Filesize Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - H…
Article Board of Supervisors 2026-01-22
Motion to approve a partial payment for the Solids Handling Upgrade for HVAC work to Lugaila Mechanical, Inc. in the amount of $55,100.88. Votes: Yes 4 , No 0 , Abstain 0 Connect With Us © PROVOX Systems, Inc. --- Menu Welcome Municipality Committe…