Solids Handling Upgrade

Project Multi-phase Cranberry Township wastewater treatment (Brush Creek WPCF) upgrade project 152 mentions · 2026-01-22 to 2026-11-19
McCurley Houston Electric Inc Kukurin Contracting Inc Community Park Community Park North Improvements Cranberry Township Board of Supervisors Shipley Plumbing LLC Lugaila Mechanical Inc Franklin Acres Pump Station Thomas Construction Inc North Boundary Park North Boundary Park Soccer Field Turf Improvements Graham Park Bruce Mazzoni Anthony Bertolino Pin Oak Court
Article Board of Supervisors 2026-11-19
12. Contract Order #2026-540 - Contract Award – Route 19 Waterline Replacement Inspection 455/2026 Services At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a contract award…
Article Board of Supervisors 2026-11-19
16. Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - HVAC 443/2026 At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handl…
Article Board of Supervisors 2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a change order for the Pin Oak Court Waterline Replacement Project to W.A. Petrakis Contracting, LLC. for a deduction in the…
Article Board of Supervisors 2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a contract award for the Park Fire Station Sign Update. Bids are being accepted on December 3, 2026. 12. Contract O…
Article Board of Supervisors 2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. 16. Con…
Article Board of Supervisors 2026-11-19
12. Contract Order #2026-540 - Contract Award - Route 19 Waterline Replacement Inspection 455/2026 Services At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a contract award…
Article Board of Supervisors 2026-11-19
16. Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - HVAC 443/2026 At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handl…
Article Board of Supervisors 2026-11-05
Motion to approve a change order for the Pin Oak Court Waterline Replacement Project to W.A. Petrakis Contracting, LLC in the amount of $14,851.50. Contract Payments 17. Contract Order #2025-48 - Partial Payment - S…
Article Board of Supervisors 2026-11-05
Motion to approve a change order for the Pin Oak Court Waterline Replacement Project to W.A. Petrakis Contracting, LLC in the amount of $14,851.50. Contract Payments 17. Contract Order #2025-48 - Partial Payment - S…
Article Board of Supervisors 2026-11-05
Motion to approve a change order for the Pin Oak Court Waterline Replacement Project to W.A. Petrakis Contracting, LLC in the amount of $14,851.50. Contract Payments 17. Contract Order #2025-48 - Partial Payment - S…
Article Board of Supervisors 2026-11-05
11/4/2026 3:19 PM Page 3 of 7 Regular Meeting 11/5/2026 Contract Payments 17. Contract Order #2025-48 - Partial Payment - Solids Handling Upgrade - General Contracto…
Article Board of Supervisors 2026-10-29
16. Contract Order #2025-182 - Change Order - Community Park North Improvements - 413/2026 Electrical At the November 5, 2026 Regular meeting, the Board will be asked to consider a change order for electrical work …
Article Board of Supervisors 2026-10-29
16. Contract Order #2025-182 - Change Order - Community Park North Improvements - 413/2026 Electrical At the November 5, 2026 Regular meeting, the Board will be asked to consider a change order for electrical work …
Article Board of Supervisors 2026-10-29
16. Contract Order #2025-182 - Change Order - Community Park North Improvements - 413/2026 Electrical At the November 5, 2026 Regular meeting, the Board will be asked to consider a change order for electrical work …
Article Board of Supervisors 2026-10-29
10/28/2026 4:57 PM Page 3 of 9 Agenda Preparation Meeting 10/29/2026 order for general construction for Community Park North Improvements to Thomas …
Article Board of Supervisors 2026-10-29
19. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical 397/2026 At the November 5, 2026 Regular meeting, the Board will be asked to consider a partial payment for the Solids Handling Upg…
Article Board of Supervisors 2026-10-01
Motion to approve a change order for general construction for Community Park North Improvements to Thomas Construction, Inc. in the amount of $68,979.31. 6. Contract Order #2025-181 - Change Order - Community Park N…
Article Board of Supervisors 2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to McCurley Houston Electric Inc. in the amount of $100,260.00. 11. Contract Order #2025-180 - Partial Payment - Community Park N…
Article Board of Supervisors 2026-10-01
Motion to approve a change order for the Goehring Road Waterline Extension to Heckman Diversified Construction in the amount of $1,810.80. Attachments Name Download Ext. Filesize Contract Order #2026-383 - Change Order - Goehring Road Waterline Exten…
Article Board of Supervisors 2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $2,502,010.80. Attachments Name Download Ext. Filesize Contract Order #2025-48 - Partial Payment - Solids H…
Article Board of Supervisors 2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to McCurley Houston Electric Inc. in the amount of $100,260.00. Attachments Name Download Ext. Filesize Contract Order #2025-51 - Partial Payment - Solids Handlin…
Article Board of Supervisors 2026-10-01
6. Contract Order #2025-180 - Change Order - Community Park North Improvements - 366/2026 General Contractor Motion to approve a change order for general construction for Community Park North Improvements to Thoma…
Article Board of Supervisors 2026-10-01
11. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical 358/2026 Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to McCurley Houston Electric Inc. …
Article Board of Supervisors 2026-09-24
11. Contract Order #2025-181 - Change Order - Community Park North Improvements - 360/2026 Plumbing At the October 1, 2026 Regular meeting, the Board will be asked to consider approval of a change order for plumbin…
Article Board of Supervisors 2026-09-24
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical 358/2026 At the October 1, 2026 Regular meeting, the Board will be asked to consider approval for a partial payment for the Solids …
Article Board of Supervisors 2026-09-24
Menu Welcome Municipality Committees Members Meeting Calendar Meeting Search Agenda Items Search Login Username: Password: Log in Back Agenda Item Details Contract Order #2025-48 - Partial Payment - Solids Handling Upgrade - General Contractor Number…
Article Board of Supervisors 2026-09-24
Menu Welcome Municipality Committees Members Meeting Calendar Meeting Search Agenda Items Search Login Username: Password: Log in Back Agenda Item Details Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical Number: 358/20…
Article Board of Supervisors 2026-09-24
At the October 1, 2026 Regular meeting, the Board will be asked to consider approval of a change order for plumbing work for Community Park North Improvements to Shipley Plumbing, LLC in the amount of $14,196.43. …
Article Board of Supervisors 2026-09-24
partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $2,502,010.80. 17. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Elect…
Article Board of Supervisors 2026-09-03
Contract Change Order 9. Contract Order #2026-314 - Change Order - Community Park Ballfields 3 & 4 Infield Turf 320/2026 Improvements Motion to approve a change order for the Community Park Ballfields 3 & 4 Infield Turf …
Article Board of Supervisors 2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for plumbing work to Shipley Plumbing LLC in the amount of $18,754.20. 14. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Elec…
Article Board of Supervisors 2026-09-03
Motion to approve a change order for the Graham Park Pickleball Court Acrylic Surfacing Project to Seal Pro in the amount of $7,040.00. Attachments Name Download Ext. Filesize Contract Order #2026-374 – Change Order - Graham Park Pickleball Court Acr…
Article Board of Supervisors 2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00. Attachments Name Download Ext. Filesize Contract Order #2025-48 - Partial Payment - Solids Han…
Article Board of Supervisors 2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for plumbing work to Shipley Plumbing LLC in the amount of $18,754.20. Attachments Name Download Ext. Filesize Contract Order #2025-50 - Partial Payment - Solids Handling Upgrade - P…
Article Board of Supervisors 2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to McCurley Houston Electric Inc. in the amount of $121,705.97. Attachments Name Download Ext. Filesize Contract Order #2025-51 - Partial Payment - Solids Handlin…
Article Board of Supervisors 2026-09-03
Motion to approve a contract award for the lining of 20 sanitary sewer manholes to State Pipe Services, Inc, via a Co-Stars contract, in the amount of $90,267.80. Contract Change Order 10. Contract Order #2026-314 -…
Article Board of Supervisors 2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00. 14. Contract Order #2025-50 - Partial Payment - Solids Handli…
Article Board of Supervisors 2026-09-03
Motion by: Bertolino, Anthony Second by: Skorupan, John Supervisor YES NO ABSTAIN Anthony Bertolino X Bruce Mazzoni X Karen Newpol X John Skorupan …
Article Board of Supervisors 2026-09-03
Motion by: Bertolino, Anthony Second by: Skorupan, John Supervisor YES NO ABSTAIN Anthony Bertolino X Bruce Mazzoni X Karen Newpol X John Skorupan …
Article Board of Supervisors 2026-09-03
Motion to approve a contract award for the lining of 20 sanitary sewer manholes to State Pipe Services, Inc, via a Co-Stars contract, in the amount of $90,267.80. Contract Change Order 10. Contract Order #2026-314 -…
Article Board of Supervisors 2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00. 14. Contract Order #2025-50 - Partial Payment - Solids Handli…
Article Board of Supervisors 2026-08-27
8/21/2026 4:22 PM Page 2 of 8 Agenda Preparation Meeting 8/27/2026 At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of …
Article Board of Supervisors 2026-08-27
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of…
Article Board of Supervisors 2026-08-27
Menu Welcome Municipality Committees Members Meeting Calendar Meeting Search Agenda Items Search Login Username: Password: Log in Back Agenda Item Details Contract Order #2025-48 - Partial Payment - Solids Handling Upgrade - General Contractor Number…
Article Board of Supervisors 2026-08-27
Menu Welcome Municipality Committees Members Meeting Calendar Meeting Search Agenda Items Search Login Username: Password: Log in Back Agenda Item Details Contract Order #2025-50 - Partial Payment - Solids Handling Upgrade - Plumbing Number: 328/2026…
Article Board of Supervisors 2026-08-27
Menu Welcome Municipality Committees Members Meeting Calendar Meeting Search Agenda Items Search Login Username: Password: Log in Back Agenda Item Details Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical Number: 329/20…
Article Board of Supervisors 2026-08-27
11. Contract Order #2026-354 – Change Order - 2026 Paving Program – Superpave Street 326/2026 Resurfacing At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of a change order for…
Article Board of Supervisors 2026-08-27
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical 329/2026 At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids…
Article Board of Supervisors 2026-08-27
12. Contract Order #2026-374 – Change Order - Graham Park Pickleball Court Acrylic Surfacing Project At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of a change order for the Graham …
Article Board of Supervisors 2026-08-27
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of a partial payment for the Solids Handling Upgrade for …