Solids Handling Upgrade
Project
Multi-phase Cranberry Township wastewater treatment (Brush Creek WPCF) upgrade project
152 mentions
· 2026-01-22 to 2026-11-19
Related
Appearances (50)
Article
Board of Supervisors
2026-11-19
12. Contract Order #2026-540 - Contract Award – Route 19 Waterline Replacement Inspection
455/2026 Services
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a contract award…
Article
Board of Supervisors
2026-11-19
16. Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - HVAC
443/2026
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids Handl…
Article
Board of Supervisors
2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a change order for the Pin Oak Court Waterline Replacement Project to W.A. Petrakis
Contracting, LLC. for a deduction in the…
Article
Board of Supervisors
2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a contract award for the Park Fire Station Sign Update. Bids are being accepted on
December 3, 2026.
12. Contract O…
Article
Board of Supervisors
2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin
Contracting, Inc.
16. Con…
Article
Board of Supervisors
2026-11-19
12. Contract Order #2026-540 - Contract Award - Route 19 Waterline Replacement Inspection
455/2026 Services
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a contract award…
Article
Board of Supervisors
2026-11-19
16. Contract Order #2025-49 - Partial Payment - Solids Handling Upgrade - HVAC
443/2026
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids Handl…
Article
Board of Supervisors
2026-11-05
Motion to approve a change order for the Pin Oak Court Waterline Replacement Project to
W.A. Petrakis Contracting, LLC in the amount of $14,851.50.
Contract Payments
17. Contract Order #2025-48 - Partial Payment - S…
Article
Board of Supervisors
2026-11-05
Motion to approve a change order for the Pin Oak Court Waterline Replacement Project to
W.A. Petrakis Contracting, LLC in the amount of $14,851.50.
Contract Payments
17. Contract Order #2025-48 - Partial Payment - S…
Article
Board of Supervisors
2026-11-05
Motion to approve a change order for the Pin Oak Court Waterline Replacement Project to
W.A. Petrakis Contracting, LLC in the amount of $14,851.50.
Contract Payments
17. Contract Order #2025-48 - Partial Payment - S…
Article
Board of Supervisors
2026-11-05
11/4/2026 3:19 PM Page 3 of 7
Regular Meeting
11/5/2026
Contract Payments
17. Contract Order #2025-48 - Partial Payment - Solids Handling Upgrade - General Contracto…
Article
Board of Supervisors
2026-10-29
16. Contract Order #2025-182 - Change Order - Community Park North Improvements -
413/2026 Electrical
At the November 5, 2026 Regular meeting, the Board will be asked to consider a change
order for electrical work …
Article
Board of Supervisors
2026-10-29
16. Contract Order #2025-182 - Change Order - Community Park North Improvements -
413/2026 Electrical
At the November 5, 2026 Regular meeting, the Board will be asked to consider a change
order for electrical work …
Article
Board of Supervisors
2026-10-29
16. Contract Order #2025-182 - Change Order - Community Park North Improvements -
413/2026 Electrical
At the November 5, 2026 Regular meeting, the Board will be asked to consider a change
order for electrical work …
Article
Board of Supervisors
2026-10-29
10/28/2026 4:57 PM Page 3 of 9
Agenda Preparation Meeting
10/29/2026
order for general construction for Community Park North Improvements to Thomas
…
Article
Board of Supervisors
2026-10-29
19. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
397/2026
At the November 5, 2026 Regular meeting, the Board will be asked to consider a partial
payment for the Solids Handling Upg…
Article
Board of Supervisors
2026-10-01
Motion to approve a change order for general construction for Community Park North
Improvements to Thomas Construction, Inc. in the amount of $68,979.31.
6. Contract Order #2025-181 - Change Order - Community Park N…
Article
Board of Supervisors
2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to
McCurley Houston Electric Inc. in the amount of $100,260.00.
11. Contract Order #2025-180 - Partial Payment - Community Park N…
Article
Board of Supervisors
2026-10-01
Motion to approve a change order for the Goehring Road Waterline Extension to Heckman Diversified Construction in the amount of $1,810.80.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-383 - Change Order - Goehring Road Waterline Exten…
Article
Board of Supervisors
2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $2,502,010.80.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-48 - Partial Payment - Solids H…
Article
Board of Supervisors
2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to McCurley Houston Electric Inc. in the amount of $100,260.00.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-51 - Partial Payment - Solids Handlin…
Article
Board of Supervisors
2026-10-01
6. Contract Order #2025-180 - Change Order - Community Park North Improvements -
366/2026 General Contractor
Motion to approve a change order for general construction for Community Park North
Improvements to Thoma…
Article
Board of Supervisors
2026-10-01
11. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
358/2026
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to
McCurley Houston Electric Inc. …
Article
Board of Supervisors
2026-09-24
11. Contract Order #2025-181 - Change Order - Community Park North Improvements -
360/2026 Plumbing
At the October 1, 2026 Regular meeting, the Board will be asked to consider approval of a
change order for plumbin…
Article
Board of Supervisors
2026-09-24
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
358/2026
At the October 1, 2026 Regular meeting, the Board will be asked to consider approval for a
partial payment for the Solids …
Article
Board of Supervisors
2026-09-24
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2025-48 - Partial Payment - Solids Handling Upgrade - General Contractor
Number…
Article
Board of Supervisors
2026-09-24
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
Number:
358/20…
Article
Board of Supervisors
2026-09-24
At the October 1, 2026 Regular meeting, the Board will be asked to consider approval of a
change order for plumbing work for Community Park North Improvements to Shipley
Plumbing, LLC in the amount of $14,196.43.
…
Article
Board of Supervisors
2026-09-24
partial payment for the Solids Handling Upgrade for general contracting work to Kukurin
Contracting, Inc. in the amount of $2,502,010.80.
17. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Elect…
Article
Board of Supervisors
2026-09-03
Contract Change Order
9. Contract Order #2026-314 - Change Order - Community Park Ballfields 3 & 4 Infield Turf
320/2026 Improvements
Motion to approve a change order for the Community Park Ballfields 3 & 4 Infield Turf
…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for plumbing work to
Shipley Plumbing LLC in the amount of $18,754.20.
14. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Elec…
Article
Board of Supervisors
2026-09-03
Motion to approve a change order for the Graham Park Pickleball Court Acrylic Surfacing Project to Seal Pro in the amount of $7,040.00.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-374 – Change Order - Graham Park Pickleball Court Acr…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-48 - Partial Payment - Solids Han…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for plumbing work to Shipley Plumbing LLC in the amount of $18,754.20.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-50 - Partial Payment - Solids Handling Upgrade - P…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to McCurley Houston Electric Inc. in the amount of $121,705.97.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-51 - Partial Payment - Solids Handlin…
Article
Board of Supervisors
2026-09-03
Motion to approve a contract award for the lining of 20 sanitary sewer manholes to State
Pipe Services, Inc, via a Co-Stars contract, in the amount of $90,267.80.
Contract Change Order
10. Contract Order #2026-314 -…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general
contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00.
14. Contract Order #2025-50 - Partial Payment - Solids Handli…
Article
Board of Supervisors
2026-09-03
Motion by: Bertolino, Anthony
Second by: Skorupan, John
Supervisor YES NO ABSTAIN
Anthony Bertolino X
Bruce Mazzoni X
Karen Newpol X
John Skorupan …
Article
Board of Supervisors
2026-09-03
Motion by: Bertolino, Anthony
Second by: Skorupan, John
Supervisor YES NO ABSTAIN
Anthony Bertolino X
Bruce Mazzoni X
Karen Newpol X
John Skorupan …
Article
Board of Supervisors
2026-09-03
Motion to approve a contract award for the lining of 20 sanitary sewer manholes to State
Pipe Services, Inc, via a Co-Stars contract, in the amount of $90,267.80.
Contract Change Order
10. Contract Order #2026-314 -…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general
contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00.
14. Contract Order #2025-50 - Partial Payment - Solids Handli…
Article
Board of Supervisors
2026-08-27
8/21/2026 4:22 PM Page 2 of 8
Agenda Preparation Meeting
8/27/2026
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
…
Article
Board of Supervisors
2026-08-27
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids Handling Upgrade for general contracting work to Kukurin
Contracting, Inc. in the amount of…
Article
Board of Supervisors
2026-08-27
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2025-48 - Partial Payment - Solids Handling Upgrade - General Contractor
Number…
Article
Board of Supervisors
2026-08-27
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2025-50 - Partial Payment - Solids Handling Upgrade - Plumbing
Number:
328/2026…
Article
Board of Supervisors
2026-08-27
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
Number:
329/20…
Article
Board of Supervisors
2026-08-27
11. Contract Order #2026-354 – Change Order - 2026 Paving Program – Superpave Street
326/2026 Resurfacing
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
a change order for…
Article
Board of Supervisors
2026-08-27
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
329/2026
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids…
Article
Board of Supervisors
2026-08-27
12. Contract Order #2026-374 – Change Order - Graham Park Pickleball Court
Acrylic Surfacing Project
At the September 3, 2026 Regular meeting, the Board will be asked to consider
approval of a change order for the Graham …
Article
Board of Supervisors
2026-08-27
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
At the September 3, 2026 Regular meeting, the Board will be asked to consider
approval of a partial payment for the Solids Handling Upgrade for …