Board of Supervisors
2026-11-19
12. Contract Order #2026-540 - Contract Award – Route 19 Waterline Replacement Inspection
455/2026 Services
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a contract award…
Article
Board of Supervisors
2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for electrical work for Community Park North Improvements to McCurley
Houston Electric, Inc. in the amount…
Article
Board of Supervisors
2026-11-19
Motion to approve a contract award for the Route 19 Waterline Replacement Project -
Phase 1 to W.A. Perkins Contracting, LLC in the amount of $1,846,486.90.
11. Contract Order #2026-534 - Contract Award – Park Fire St…
Article
Board of Supervisors
2026-11-19
22. Contract Order #2025-181 - Final Payment - Community Park North Improvements -
442/2026 Plumbing
At the December 10, 2026, Regular meeting, the Board will be asked to consider approval of
a final payment for pl…
Article
Board of Supervisors
2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a contract award for the Park Fire Station Sign Update. Bids are being accepted on
December 3, 2026.
12. Contract O…
Article
Board of Supervisors
2026-11-19
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a final payment for plumbing work for Community Park North Improvements to Shipley
Plumbing, LLC.
24. Contract Orde…
Article
Board of Supervisors
2026-11-19
12. Contract Order #2026-540 - Contract Award - Route 19 Waterline Replacement Inspection
455/2026 Services
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a contract award…
Article
Board of Supervisors
2026-11-19
24. Contract Order #2026-313 - Final Payment - North Boundary Park Soccer Field Turf
435/2026 Improvements
At the December 10, 2026 Regular meeting, the Board will be asked to consider approval of
a final payment f…
Article
Board of Supervisors
2026-10-01
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to
McCurley Houston Electric Inc. in the amount of $100,260.00.
11. Contract Order #2025-180 - Partial Payment - Community Park N…
Article
Board of Supervisors
2026-10-01
Motion to approve a partial payment for general construction for Community Park North Improvements to Thomas Construction, Inc. in the amount of $277,901.61.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-180 - Partial Payment – Communi…
Article
Board of Supervisors
2026-10-01
Motion to approve a partial payment for turf improvements to Playing Surface Solutions, Inc. in the amount of $303,307.13.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf Impr…
Article
Board of Supervisors
2026-10-01
11. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
358/2026
Motion to approve a partial payment for the Solids Handling Upgrade for electrical work to
McCurley Houston Electric Inc. …
Article
Board of Supervisors
2026-09-24
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
358/2026
At the October 1, 2026 Regular meeting, the Board will be asked to consider approval for a
partial payment for the Solids …
Article
Board of Supervisors
2026-09-24
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2026-313 - Partial Payment - North Boundary Park Soccer Field Turf Improvements…
Article
Board of Supervisors
2026-09-24
partial payment for the Solids Handling Upgrade for general contracting work to Kukurin
Contracting, Inc. in the amount of $2,502,010.80.
17. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Elect…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for plumbing work to
Shipley Plumbing LLC in the amount of $18,754.20.
14. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Elec…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for electrical work for Community Park North Improvements to McCurley Houston Electric, Inc. in the amount of $25,419.10.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-182 - Partial Payment – Communi…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for turf improvements to Playing Surface Solutions, Inc. in the amount of $349,629.18.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf Impr…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general
contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00.
14. Contract Order #2025-50 - Partial Payment - Solids Handli…
Article
Board of Supervisors
2026-09-03
18. Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field
Turf Improvements
Motion to approve a partial payment for turf improvements to Playing Surface
Solutions, Inc. in the amount of $349,629.18…
Article
Board of Supervisors
2026-09-03
Motion to approve a partial payment for the Solids Handling Upgrade for general
contracting work to Kukurin Contracting, Inc. in the amount of $720,360.00.
14. Contract Order #2025-50 - Partial Payment - Solids Handli…
Article
Board of Supervisors
2026-08-27
8/21/2026 4:22 PM Page 3 of 8
Agenda Preparation Meeting
8/27/2026
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
…
Article
Board of Supervisors
2026-08-27
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf Improvements…
Article
Board of Supervisors
2026-08-27
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
329/2026
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids…
Article
Board of Supervisors
2026-08-27
18. Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field
Turf Improvements
At the September 3, 2026 Regular meeting, the Board will be asked to consider
approval of a partial payment for turf impr…
Article
Board of Supervisors
2026-08-27
15. Contract Order #2025-51 - Partial Payment - Solids Handling Upgrade - Electrical
329/2026
At the September 3, 2026 Regular meeting, the Board will be asked to consider approval of
a partial payment for the Solids…
Article
Board of Supervisors
2026-08-06
Motion to authorization the advertisement of a public hearing and intention to adopt Bill
No. 2026-05 Ordinance Amendment for Chapter 27 (Zoning).
Parks & Recreation and Library - Vice Chair Newpol
Public Works and Enginee…
Article
Board of Supervisors
2026-08-06
33. Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf
284/2026 Improvements
Motion to approve a partial payment for turf improvements to Playing Surface Solutions,
Inc. in the amoun…
Article
Board of Supervisors
2026-08-06
Motion to approve a change order for the Solids Handling Upgrade for general contracting work to Kukurin Contracting, Inc. in the amount of $173,960.35.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-48 - Change Order - Solids Handling …
Article
Board of Supervisors
2026-08-06
Motion to approve a change order for turf improvements to Playing Surface Solutions, Inc. in the amount of $13,327.77.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-313 - Change Order – North Boundary Park Soccer Field Turf Improvement…
Article
Board of Supervisors
2026-08-06
Motion to approve a partial payment for electrical work for Community Park North Improvements to McCurley Houston Electric, Inc. in the amount of $135,709.24.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-182 - Partial Payment – Commun…
Article
Board of Supervisors
2026-08-06
Motion to approve a partial payment for turf improvements to Playing Surface Solutions, Inc. in the amount of $289,275.36.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf Impr…
Article
Board of Supervisors
2026-08-06
23. Contract Order #2025-48 - Change Order - Solids Handling Upgrade - General
Contractor
Motion to approve a change order for the Solids Handling Upgrade for general
contracting work to Kukurin Contracting, Inc. in the a…
Article
Board of Supervisors
2026-08-06
34. Contract Order #2025-182 - Partial Payment – Community Park North
Improvements – Electrical
Motion to approve a partial payment for electrical work for Community Park North
Improvements to McCurley Houston Electric, I…
Article
Board of Supervisors
2026-07-30
7/29/2026 5:46 PM Page 4 of 9
Agenda Preparation Meeting
7/30/2026
300/2026
At the August 6, 2026 Regular meeting, the Board will be asked to consider approval…
Article
Board of Supervisors
2026-07-30
At the August 6, 2026 Regular meeting, the Board will be asked to consider approval of a
partial payment for electrical work for Community Park North Improvements to McCurley
Houston Electric, Inc. in the amount of…
Article
Board of Supervisors
2026-07-30
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2026-313 - Change Order – North Boundary Park Soccer Field Turf Improvements
Nu…
Article
Board of Supervisors
2026-07-30
Menu
Welcome
Municipality
Committees
Members
Meeting Calendar
Meeting Search
Agenda Items
Search
Login
Username:
Password:
Log in
Back
Agenda Item Details
Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf Improvements…
Article
Board of Supervisors
2026-07-30
19. Contract Order #2025-48 - Change Order - Solids Handling Upgrade - General
Contractor
At the August 6, 2026 Regular meeting, the Board will be asked to consider approval
of a change order for the Solids Handling Upgra…
Article
Board of Supervisors
2026-07-30
31. Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field
Turf Improvements
At the August 6, 2026 Regular meeting, the Board will be asked to consider approval
of a partial payment for turf improve…
Article
Board of Supervisors
2026-06-25
Motion to approve Purchase Approval #126 for two (2) 2026 Dodge Durangos AWD for use
by the Police Department from Laurel Motors Group, via a Co-Stars State Contract, in the
amount of $69,950.00 inclusive of the tr…
Article
Board of Supervisors
2026-06-25
Motion to approve a partial payment for electrical work for Community Park North
Improvements to McCurley Houston Electric, Inc. in the amount of $62,262.32.
28. Contract Order #2026-313 - Partial Payment – North Boun…
Article
Board of Supervisors
2026-06-25
Motion to approve a change order for the Sun Valley Waterline Replacement - Phase 3 to Metarko Excavating, LLC in the amount of $66,378.51.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-157 - Change Order - Sun Valley Waterline Replace…
Article
Board of Supervisors
2026-06-25
Motion to approve a change order for turf improvements to Playing Surface Solutions, Inc. in the amount of $14,818.45.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-313 -Change Order – North Boundary Park Soccer Field Turf Improvements…
Article
Board of Supervisors
2026-06-25
Motion to approve a partial payment for electrical work for Community Park North Improvements to McCurley Houston Electric, Inc. in the amount of $62,262.32.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2025-182 - Partial Payment – Communi…
Article
Board of Supervisors
2026-06-25
Motion to approve a partial payment for turf improvements to Playing Surface Solutions, Inc. in the amount of $117,703.78.
Attachments
Name
Download
Ext.
Filesize
Contract Order #2026-313 - Partial Payment – North Boundary Park Soccer Field Turf Impr…
Article
Board of Supervisors
2026-06-25
Motion by: Bertolino, Anthony
Second by: Newpol, Karen
Supervisor YES NO ABSTAIN
Page 7 of 21
Anthony Bertolino X
Bruce …
Article
Board of Supervisors
2026-06-25
Motion by: Bertolino, Anthony
Second by: Newpol, Karen
Supervisor YES NO ABSTAIN
Anthony Bertolino X
Page 12 of 21
Bruce Hezlep …
Article
Board of Supervisors
2026-06-04
19. Contract Order #2025-182 - Partial Payment – Community Park North
Improvements – Electrical
Motion to approve a partial payment for electrical work for Community Park North
Improvements to McCurley Houston Electric, I…
Article
Board of Supervisors
2026-06-04
19. Contract Order #2025-182 - Partial Payment – Community Park North Improvements –
191/2026 Electrical
Motion to approve a partial payment for electrical work for Community Park North